Monday, February 9, 2009

Schedule & 2 Week Look-Ahead (J8)


WBS (J8)


The Work Breakdown Structure for the Basketball Practice Facility is broken down into eight levels of mechanical description. The WBS breaks down the mechanical system into specific components relevant to its successful operation in the building. The WBS is broken down into a level-list below followed by a detailed component list. Please see Figure 1-10 for the WBS.


Meeting Minutes (S10)

Name of Organization: S-10

Purpose of Meeting: Class Time

Date/Time: January 21st, 4:00-6:45

1. Introduction to integrated lab

2. Introduction to leadership survey

3. Choose team members

Name of Organization: S-10

Purpose of Meeting: Exposure to Drawings

Date/Time: January 23nd, 1:00-2:00

1. Reviewed drawings

2. Came up with questions to ask professor/M-team

Name of Organization: S-10

Purpose of Meeting: Class Time

Date/Time: January 28th, 4:00-6:45

1. Reviewed leadership survey

2. Reviewed questions with M-team

Name of Organization: S-10

Purpose of Meeting: Work Strategy

Date/Time: February 3nd, 6:00-7:00

1. WBS

a. Columns

b. Beams

c. Bolts

d. Plates

2. Load Diagram

3. Due Feb. 8th

a. Final Assignment L1 Submittal (Revised according to M-team)

b. Final L1 PowerPoint

4. Due Feb. 9th

a. Final L1 PowerPoint Presentation (Coordinate with M-team)

Name of Organization: S-10

Purpose of Meeting: Class Time

Date/Time: February 4th, 4:00-6:45

1. Review work with M-team

2. Additional questions for Dr. McCoy/M-team

Name of Organization: S-10

Purpose of Meeting: Finalize Assignment L1

Date/Time: February 8th, 2:00-6:00

1. Revise and Complete Assignment L1 Report

2. Complete Assignment L1 PowerPoint

S10 Site Pictures

Site pictures have been uploaded to filebox.

http://filebox.vt.edu/users/jnay/Integrated%20Lab/

Meeting Minutes (J8)

Name of Organization: J-8

Purpose of Meeting: Class Time

Date/Time: January 21st, 4:00-6:45

1. Introduction to integrated lab

2. Introduction to leadership survey

3. Choose team members

Name of Organization: J-8

Purpose of Meeting: Exposure to Drawings

Date/Time: January 22nd, 5:00-5:30

1. Reviewed drawings

2. Came up with questions to ask professor/M-team

Name of Organization: J-8

Purpose of Meeting: Class Time

Date/Time: January 28th, 4:00-6:45

1. Review of leadership survey/test

2. Reviewed questions with M-team

Name of Organization: J-8

Purpose of Meeting: Break Down Assignment L1

Date/Time: February 2nd, 7:30-8:30

1. Due Feb. 5th

a. Written Mechanical System Descriptions & Flow Charts (Drawn Only)

i. Cooling & Exhaust

ii. Heating

iii. Piping

2. Due Feb. 6th

a. Leadership Survey Report

b. Flow Charts (Visio)

c. Assignment L1 Report Compilation

3. Due Feb. 8th

a. Final Assignment L1 Submittal (Revised according to M-team)

b. Final L1 PowerPoint

4. Due Feb. 9th

a. Final L1 PowerPoint Presentation (Coordinate with M-team)

Name of Organization: J-8

Purpose of Meeting: Class Time

Date/Time: February 4th, 4:00-6:45

1. Review work with M-team

2. Additional questions for Dr. McCoy/M-team

Name of Organization: J-8

Purpose of Meeting: Gathering of Information for Assignment L1

Date/Time: February 5th, 7:30-11:00

1. Compile Written Mechanical System Description

2. Produce a List of Components as Defined by Mechanical Systems

3. Produce Flow Charts of Mechanical Systems in Visio

Name of Organization: J-8

Purpose of Meeting: Finalize Assignment L1

Date/Time: February 8th, 5:30-

1. Revise and Complete Assignment L1 Report

2. Complete Assignment L1 PowerPoint

Wednesday, February 4, 2009

The blog for our team is now set up. J and S teams, please use this site to document and track progress.